Completed project · Power transformer

Power transformer transport and final placement

Southern transported this power transformer and completed Jack & Slide offloading and final placement on pad.

See the site visit and the placement ↓

361,200 lb

Executed by Southern · Documented execution

  • Jack & Slide offload
  • Final placement on pad
01 / Site visit

Review the approach.
Check the receiving ground.

Southern inspected the approach to the receiving site and reviewed culverts, turning space and the path to the transformer pad with the site team.

The report called for road and ground preparation, a follow-up site assessment and a check of the receiving conditions before entering the site.

The plan developed in the field.

An engineering study required one of the drainage culverts on the access road to be replaced before any loaded transit over it.

A bridge jumper was considered to span that culvert instead. Southern ruled it out: there was not enough ground at the sides of the road to anchor its base.

Section · Culvert crossingConsidered12CulvertApplied341Bridge jumper, ruled out2No ground to anchor the base31-3/4 in steel mats46 in compacted dirt
Illustrative · Not to scale · Not a project drawingWhy the bridge jumper was ruled out, and the protection the review called for over the culvert.

The alternative reviewed at the site meeting was to transload the transformer onto a 20-axle modular combination. It was proposed by a bridge engineer who evaluates weight capacity on state bridges, and accepted by every party present.

Southern would supply the modular trailer specifications for the weight and spacing analysis, and the weight-resistance report would be issued on the project engineering side.

That alternative carried its own requirements: every culvert along the path protected with 6 in of compacted dirt and 1-3/4 in steel mats, and every turning point into the substation widened to 35 ft.

Southern then drove and assessed a different route into the site. It would keep the transformer on the truck-and-trailer combination and run over two culverts instead of the full line, with a 16 ft roadway compacted to 95% before the move — and it removed the need for the transload.

Plan · Route comparisonOriginal roadPad1Truck and trailer20-axle modular2Reviewed alternativePad16 ft31Culverts along the road2Transload before the final approach3Two culverts, 95% compaction, no transload
Illustrative · Not to scale · Not a project drawingThe route Southern assessed, against the road the first plan had to cross.
02 / Plan and arrival

Watch the weather.
Arrive on firm ground.

The site review also required reassessment if weather changed the ground conditions before arrival.

White tractor and loaded heavy-haul trailer carrying the wrapped transformer at the receiving site
Arrival · Transformer on the transport configuration
Overhead view of the transformer and trailer positioned alongside the concrete receiving pad
Positioning · Trailer alongside the receiving pad
03 / Offloading and final placement

From the trailer
to the pad.

Elevated view of the transformer above slide tracks extending across the receiving pad
Jack & Slide · Transfer onto the pad
Power transformer resting on its concrete pad after placement
Final placement · Transformer on the pad

Plan your delivery

Start with the load and the receiving site.

Share the cargo details, origin, destination and available site information. Southern can review the transport and handling scope your delivery needs.

Start a Request →